Advanced LIGO subsystems
are the organizational units of the overall project. Follow the links below to view the mission and progress of each subsystem.
Auxiliary Optics | Core Optics |
![]() |
![]() |
Data Acquisition | Data and Computing Systems |
![]() |
![]() |
Facilities Modifications |
Input Optics |
![]() |
![]() |
Interferometer Control |
Pre-Stabilized Laser |
![]() |
![]() |
Seismic Isolation |
Suspensions |
![]() |
![]() |
Advanced LIGO News
One-Arm Test Yields Encouraging Results
November 2012
LIGO Hanford's one-arm test closed in September 2012 with its primary goals successfully completed and with a storehouse of results that will guide future installation and commissioning. The LIGO commissioning team tasked with the test obtained a substantial list of outcomes, some highlights of which included the following.
The one-arm test didn't exercise some of these systems to their fullest degree and plenty of additional commissioning lies ahead. The ITM and ETM hang in four-stage suspensions that provide noise cancellation at each stage (adjacent photo), but only a subset of the controls were deployed to stabilize the mirrors. The green laser light injected at the end station wasn't synchronized to the main (infrared) laser in the corner station as will be the case for future tests. Instead, a spare infrared laser and reference cavity in the corner station sent light through a 4km optical fiber to the end station, where it was converted to green. Noise on the light from the reference system and the optical fiber was visible at higher frequencies throughout the test. Seismic noise clearly manifested itself at frequencies below 1 Hz; a more complete mitigation effort will include additional feedback that becomes available when the full arm length stabilization controls enter the mix over the next year.
Hanford will next undertake a half-interferometer test on the Y arm (HIFO-Y) that will include all of the one-arm components plus the main laser, the suspended mode cleaner and the power recycling optics that lie between the laser and the beam splitter. Installation of these items is currently underway; watch for news of HIFO-Y in the summer of 2013.
aLIGO News Archive
August 2016 -- LIGO Reports O1 Results
June 2016 -- Another Black Hole Merger
Feburary 2016 -- First Gravitational Wave Detection
November 2015 -- O1 Progress Report
August 2015 -- Final Preparations for the O1 Run
February 2015 -- Hanford's H1 Achieves Two-Hour Lock
July 2014 -- Livingston Commissioning Progress
June 2014 -- Livingston Locks the L1 Interferometer
December 2013 -- Livingston Installs End Station Payloads
September 2013 -- Half-interferometer Test Closes
June 2013 -- DRMI Test at Livingston
May 2013 -- Arm Length Stabilization
November 2012 -- One-arm Test at Hanford
September 2012 -- LIGO Begins Locking Optical Cavities
August 2012 -- Installation of Stray Light Controls
July 2012 -- Small Optic Suspenions Enter L1
April 2012 -- First Cartridges Enter the Vacuum
November 2011 -- Glass Fiber Suspensions in Production
October 2011 -- Continued Suspension Development
July 2011 -- Hanford's H2 Becomes a 4K
May 2011 -- LLO Laser Installation Completed
March 2011 -- Input and Output Tubes Undergo Removal
February 2011 -- New Laser Enclosure Takes Shape
December 2010 -- Initial LIGO Comes Out of the Vacuum
October 2010 -- S6 Yields to Advanced LIGO
Explore Advanced LIGO
Construction Schedule
Instrumentation and Astrophysics
An Overview of the Upgrades
The International Partnership
Science Impacts
LIGO Technology Transfers
LIGO Scientific Collaboration
Public Outreach
LIGO Magazine
aLIGO Home